The reconstruction of the kindergarten in Sanchursk is 40% complete.
Reconstruction of the Teremok kindergarten in Sanchursk continues. It includes the construction of an annex for the kitchen. The work is being carried out with funds from the regional budget. The contract was concluded with Oreon LLC (Mari El) with a completion date of September 30, 2026.
As of today, the project is 40% complete. Workers have completed the foundation, the brick wall masonry, and the installation of external heating and water supply networks. Work is currently underway on the roof, and installation of internal engineering systems is in progress. The heating system is 35% complete, and the water supply system is 70% complete.