Sewage collector is being "repaired" in Sidorovka
According to the Municipal Unitary Enterprise, the sewer collector, built in the 70s of the last century, needed urgent renovation due to significant wear and an increase in the number of defects in the drainage network. In this regard, the Municipal Unitary Enterprise has decided to carry out major repairs of the collector.
The company's specialists replaced an old steel pipe with a diameter of 110 mm with two pipelines (left and right thread). Pipelines are modern polyethylene pipes with a total length of 350 meters. At the next stage of the repair, two more parallel pipes with a total length of 400 meters will be laid. "This solution will ensure the reliability and durability of the village's drainage system," Vodokanal said.
Work on the collector is planned to be completed by the end of this year. The launch of a new pressure collector should ensure the stable operation of the village's sewage treatment plants and increase the level of sanitary safety for its residents.
Другие Новости Кирова (НЗК)






Sewage collector is being "repaired" in Sidorovka
Municipal Unitary Enterprise Vodokanal has begun major repairs of the sewage pressure collector in the village of Sidorovka.