Bridge repairs in Nagorsky District are nearing completion.

Bridge repairs in Nagorsky District are nearing completion.

      In Nagorsky District, repairs to the bridge over the Kobra River are nearing completion. Its length is 202.3 linear meters. It should be noted that this is the first repair since the bridge was commissioned. According to the government, a structural inspection was carried out in 2023. Experts found it to be in unsatisfactory condition. The bridge is to be fully restored — from the supports and spans to the drainage system and guardrails. As of today, the right side is complete; waterproofing has been applied to the left side, and guardrail elements are being installed.