In the Kirov region, roads to Mari El and Nizhny Novgorod region are being repaired.
In the Kirov region, plans are underway to improve three roads leading to other regions. This was reported by the Ministry of Transport. All work is promised to be completed by August 31, 2026.
Thus, in 2026, 3.4 kilometers of the Yaransk — Kiknur — Nizhny Novgorod region border road will be repaired; as of today, the leveling and top layers of asphalt have been laid, and shoulder reinforcement has begun. On the section of the Kirov — Sovetsk — Yaransk — Loshkari — Mari El border road in the Sovetsk district, the contractor is milling the old surface. Meanwhile, on the section of the Yaransk — Sanchursk — Mari El border road in the Yaransk district, 1.8 kilometers long, the top layer of asphalt concrete is being laid.
Другие Новости Кирова (НЗК)
In the Kirov region, roads to Mari El and Nizhny Novgorod region are being repaired.
The Ministry of Transport reported on the progress of the work.