The readiness of the cafeteria in the kindergarten in Sanchursk is 83%.
The reconstruction of the kindergarten "Teremok" continues in Sanchursk. The progress of the work is being monitored by the Ministry of Construction of the Kirov Region. The work is being funded by the regional budget.
The reconstruction includes the construction of an extension for the placement of the food block. Its area is 1,437 square meters. The construction readiness of the facility is 83%.
Currently, the interior finishing work has been completed. Previously, heating, water supply, and electricity supply networks were installed, windows and an automatic fire alarm system were installed, and the roof was completed. Now the installation of ventilation and video surveillance systems is underway, and it is planned to be completed by the end of next week. The contractor has also begun landscaping the area, which will last for 1.5 months.
Другие Новости Кирова (НЗК)
The readiness of the cafeteria in the kindergarten in Sanchursk is 83%.
The Ministry of Construction reported on the progress of the work.