Recently, the Minister of Environmental Protection Timur Abashev and the environmental prosecutor Oleg Olin inspected the construction progress of the waste sorting complex "Central." It is worth noting that they plan to sort about 2/3 of all waste in the Kirov region — approximately 200,000 tons per year.
During the inspection, it was revealed that workers are currently constructing the main production building, installing the administrative and household building, and setting up technological equipment (bag openers and conveyor lines). To date, a modular boiler house has been installed. The arrangement of the fire reservoir is nearing completion. In addition, the contractor is bringing in additional equipment.