Two years without a clinic: contractor forced to pay 5 million for the stalled construction
As reported by the Kirov Region prosecutor's office, in March 2022 a contract worth more than 360 million rubles was signed between the Slobodskoy Central District Hospital and a contractor for the construction of a children's polyclinic.
Initially the construction was to be completed by December 1, 2023, but the deadlines were missed. Work was halted several times, which drew the attention of the Slobodskoy interdistrict prosecutor's office.
During its inspection the prosecutor's office uncovered violations and initiated an administrative offense case. The contractor was fined more than 5 million rubles, and a criminal case on fraud was opened against the company's director.
In May 2025 a new contractor was found to complete the project, and a contract was signed with them for 117 million rubles. Thanks to the prosecutor's intervention, the work was finished and the polyclinic received a permit for commissioning.
Другие Новости Кирова (НЗК)





Two years without a clinic: contractor forced to pay 5 million for the stalled construction
A children's polyclinic in Slobodskoy was completed after the prosecutor's office intervened.