"T Plus" inspected 94% of the heat networks in Kirov, Kirovo-Chepetsk, and Slobodskoy.

      94% of heat networks in Kirov, Kirovo-Chepetsk, and Slobodsk were tested under increased pressure. According to "T Plus," all necessary work has been completed on 413 out of 573 sections of heat pipelines (72%), and the networks are ready to withstand winter loads. Work is ongoing on the remaining sections: after defect elimination, re-tests will be conducted. The company noted that on Wednesday, July 30, specialists pressure-tested three sections near the "Rodina" House of Culture in Kirov. Today, July 31, they plan to test two more sections of the heat network near Andrey Uputa Street. It should be noted that current information on scheduled testing dates and ongoing repairs can be clarified here.