Moscow Street in Kirov will be expanded to six lanes.

Moscow Street in Kirov will be expanded to six lanes.

      The Kirov administration has approved the documentation for the planning of the street and road network area of Moskovskaya Street — from Theater Square to Builders Avenue. The resolution was signed on July 6, 2026, and published for public access.

      The project involves a comprehensive reconstruction of the highway, which is divided into three sections with different parameters.

      On the segment from Builders Avenue to Solnechnaya Street, the roadway will be widened to 24 meters with the organization of six lanes (3.5 meters each). A 2-meter-wide median strip with a barrier fence will also be added, along with edge safety strips of 0.5 meters on each side.

      On the section from Solnechnaya Street to Oktyabrsky Avenue, the road width will increase to 18 meters — up to four lanes. The edge strips here will be wider — 2 meters each.

      On the segment from Oktyabrsky Avenue to Derendyayeva Street, widening is not planned due to the proximity of residential building No. 57 on Moskovskaya. Instead, the possibility of organizing one-way traffic with a connection to a "ring" with Engels Street is being considered.

      The project also includes:

      - the construction of pull-in pockets at public transport stops;

      - the organization of additional parking spaces;

      - the construction of underground pedestrian crossings near bus stops;

      - an increase in the capacity of intersections through additional lanes for right and left turns, optimization of traffic light regulation, and installation of video cameras;

      - the appearance of a side road 5.5 meters wide on the section from Mendeleev Street to Lomonosov Street on the left side.

      At the intersection with Solnechnaya Street and Roman Yerdyakov Street, it is proposed to change the alignment of the latter — shifting it towards Solnechnaya. This will allow cars turning from Solnechnaya onto Roman Yerdyakov not to enter Moskovskaya, which should increase the capacity of the main highway.

      The total length of the reconstructed section is 4.2 kilometers. The calculated speed of movement is 70 km/h.

Другие Новости Кирова (НЗК)

The captain of "Dynamo" has ended his playing career. The captain of "Dynamo" has ended his playing career. Now Artem Pasko will be a sports official. A contractor has been selected for the improvement of the 50th Anniversary of the VLKSM Park. A contractor has been selected for the improvement of the 50th Anniversary of the VLKSM Park. The contract for the renovation of the park at the Palace of Pioneers has been signed with the company "AVEN-NORTH". The work is to be completed by the end of October 2027. The Muscovite who went missing in the Kirov forests had to climb a tree to save himself. The Muscovite who went missing in the Kirov forests had to climb a tree to save himself. The police located the man after his call. A contractor has been selected for the improvement of the 50th Anniversary of the VLKSM Park. A contractor has been selected for the improvement of the 50th Anniversary of the VLKSM Park. The contract for the renovation of the park at the Palace of Pioneers has been signed with the company "AVEN-NORTH". The work is to be completed by the end of October 2027. Russians were told about used cars that are not worth overpaying for. Russians were told about used cars that are not worth overpaying for. The anti-rating included models from Toyota, Kia, Hyundai, Skoda, and Volkswagen. В течение последних суток на дорогах региона произошло ДТП, в результате которого пострадали два молодых мотоциклиста. В течение последних суток на дорогах региона произошло ДТП, в результате которого пострадали два молодых мотоциклиста. 6 июля 2026 года в Кировской области зафиксировано 6 дорожно-транспортных происшествий, в результате которых один человек погиб и 8 получили травмы. Как сообщила региональная Госавтоинспекция, две из аварий произошли с участием молодых мотоциклистов. Одно из происшествий, согласно предварительным данным, произошло 6 июля 2026 года в Нововятском.

Moscow Street in Kirov will be expanded to six lanes.

The city administration has approved the planning project for the reconstruction of the highway from Theater Square to Builders Avenue. The document provides for the expansion of the roadway, the construction of underground crossings, and changes to the traffic patterns on the adjacent streets.