The water main on Lenin Street is being repaired.
A crew of four workers is replacing a damaged six-meter section of pipe. The 900 mm-diameter water main was commissioned in 1978, and a longitudinal crack was discovered that threatened the reliability of the system. A modern PFRK cast-iron coupling is being used for the repair. Its service life exceeds 50 years, which will significantly improve the durability and safety of the water supply network. An excavator and a dump truck are being used on site. All work is being carried out without shutting off the cold water supply.
Другие Новости Кирова (НЗК)





The water main on Lenin Street is being repaired.
On August 19, specialists from the municipal water utility Vodokanal began repairing the main pipeline at 205 Lenin Street.