In the Verkhnekamsk district, they promise to complete the road for 202 million by autumn.
In the Verkhnekamsky District, the repair of a section of the road Omutninsk — Peskovka — Kirs, stretching 7.3 kilometers, continues. The progress of the work was reported by the Ministry of Transport.
Currently, the contractor "Vyatavtodor" is laying the top layer of asphalt in the area of the village of Gar. Next, it is planned to strengthen the shoulders with gravel and apply road markings. Reversible traffic has been organized on the road.
It should be noted that the work is to be completed by August 31, 2026. The cost is 202.27 million rubles. The warranty period is three months for paint markings, one year for thermoplastic markings, and eight years for the road surface and shoulder reinforcement.
Другие Новости Кирова (НЗК)
In the Verkhnekamsk district, they promise to complete the road for 202 million by autumn.
The length of the section is 7.3 kilometers.