The tunnel pit in Novovyatsk is 80% ready.
In the Novovyatsky district of Kirov, the construction of a tunnel under the Trans-Siberian Railway continues. Currently, the excavation for the tunnel is 80% complete, and the protective screen is 50% complete. Workers are engaged in creating retaining walls, laying concrete and geotextiles, installing the reinforced framework of the slopes, and filling the pipes of the protective screen.
In the coming days, the construction of the main road will begin. The contractor plans to complete the driving of piles and start the excavation and removal of soil from the tunnel around July-August.
According to Deputy Prime Minister Alexey Petryakov, work is being carried out simultaneously from both sides. More than 100 people are working on the site. Both authorial and construction control have been organized.